GWEP AMEY/INABENSA
GWEP AMEY/INABENSA
GWEP AMEY/INABENSA
Provision of switch installation teams and OLE registration support for the installation of 102 switches across the GWEP route.
Provision of switch installation teams and OLE registration support for the installation of 102 switches across the GWEP route.
Provision of switch installation teams and OLE registration support for the installation of 102 switches across the GWEP route.
Project
ECS Rail
Project
ECS Rail
/
Client
GWEP AMEY INABENSA
Client
GWEP AMEY INABENSA
/
Duration
6 months
Duration
6 months
/
Location
GWEP ROUTE
Location
GWEP ROUTE
/
Date
Jan 2019
Date
Jan 2019


/
What we do
Nationwide Rail Project Support and OLE Expertise
Nationwide Rail Project Support and OLE Expertise
Nationwide Rail Project Support and OLE Expertise
Project Overview
Between August 2017 and January 2018, ECS delivered a major programme of works valued at approximately £1.5M for GWEP AMEY/INABENSA. The project involved supplying two dedicated switch installation teams, including full management oversight, to plan and install a total of 102 switches across the route. These comprised a range of switch types, including Track Section Switches, Circuit Main Earth & Power Supply Switches, as well as both motorised and manually operated units.
Between August 2017 and January 2018, ECS delivered a major programme of works valued at approximately £1.5M for GWEP AMEY/INABENSA. The project involved supplying two dedicated switch installation teams, including full management oversight, to plan and install a total of 102 switches across the route. These comprised a range of switch types, including Track Section Switches, Circuit Main Earth & Power Supply Switches, as well as both motorised and manually operated units.
Between August 2017 and January 2018, ECS delivered a major programme of works valued at approximately £1.5M for GWEP AMEY/INABENSA. The project involved supplying two dedicated switch installation teams, including full management oversight, to plan and install a total of 102 switches across the route. These comprised a range of switch types, including Track Section Switches, Circuit Main Earth & Power Supply Switches, as well as both motorised and manually operated units.
The Process
The ECS teams were responsible for all stages of the switch installation process, from initial planning through to final implementation. This included ensuring correct integration of various switch types to meet the technical specifications of the project. Alongside this, ECS deployed internal resources to support wiring and registration activities, enabling the project to progress in line with critical milestones. Personnel supplied included engineers, construction managers, senior supervisors, and OLEC-competent staff.
The ECS teams were responsible for all stages of the switch installation process, from initial planning through to final implementation. This included ensuring correct integration of various switch types to meet the technical specifications of the project. Alongside this, ECS deployed internal resources to support wiring and registration activities, enabling the project to progress in line with critical milestones. Personnel supplied included engineers, construction managers, senior supervisors, and OLEC-competent staff.
The ECS teams were responsible for all stages of the switch installation process, from initial planning through to final implementation. This included ensuring correct integration of various switch types to meet the technical specifications of the project. Alongside this, ECS deployed internal resources to support wiring and registration activities, enabling the project to progress in line with critical milestones. Personnel supplied included engineers, construction managers, senior supervisors, and OLEC-competent staff.
Delivery & Results
Through a combination of skilled labour, technical expertise, and effective management, ECS successfully installed all 102 switches and provided essential registration support. This work played a vital role in keeping the project on track for its commissioning schedule, ensuring all systems met the required safety and operational standards.
Through a combination of skilled labour, technical expertise, and effective management, ECS successfully installed all 102 switches and provided essential registration support. This work played a vital role in keeping the project on track for its commissioning schedule, ensuring all systems met the required safety and operational standards.
Through a combination of skilled labour, technical expertise, and effective management, ECS successfully installed all 102 switches and provided essential registration support. This work played a vital role in keeping the project on track for its commissioning schedule, ensuring all systems met the required safety and operational standards.







/
Our Approach
We bring together critical services under one roof, improving coordination, reducing risk, and unlocking long-term value.
We bring together critical services under one roof, improving coordination, reducing risk, and unlocking long-term value.
In a complex world, developments need partners who bring clarity. We unify labour, plant, power systems, and civils into a seamless delivery model, creating value through simplicity. Built for today’s demands. Engineered for tomorrow’s challenges.
In a complex world, developments need partners who bring clarity. We unify labour, plant, power systems, and civils into a seamless delivery model, creating value through simplicity. Built for today’s demands. Engineered for tomorrow’s challenges.
In a complex world, developments need partners who bring clarity. We unify labour, plant, power systems, and civils into a seamless delivery model, creating value through simplicity. Built for today’s demands. Engineered for tomorrow’s challenges.
Recent Projects
Recent Projects
Recent Projects

/
Get in Touch